WORK METHODOLOGY OF WET AREAS WATERPROOFING
(TOILETS / BALCONY / KITCHENS /
OTHERS)
Ø Concrete surfaces should be fully cured (minimum 28 days)
prior to application.
Ø The concrete surface shall be cleaned thoroughly of all
contaminants like dust, traces of curing compound, oil and grease.
Ø All surface imperfections, protrusions, structurally
unsound and friable concrete must be removed and repaired with a suitable
concrete repair mortar.
Ø All surface cracks, undulations and voids shall be repaired
appropriately before application.
Ø All cracks above 5mm deep, shall be cut opened, cleaned and shall be
filled with shrink free crack filling material. i.e. GP2 or equivalent.
Ø The entire surface to be coated must be in SSD condition
prior to application of coating.
Ø All the construction joints need to be opened and treated
with polymer modified mortar (Cement: sand: SBR Latex) or ready to use modified
mortar.
Ø Injection grout shall be done at all construction joints.
Nozzle shall be fixed @ 500mm centre to centre at all construction joints.
Ø 3
days ponding test has to be carried out, if the leakages are observed then
repeat the above procedure till to achieved water tight toilet area
STEP- 02 : SEALING OF PIPE INLET / OUTLET
DRAINAGE PIPES AND FILLING CUTOUT HOLES
Ø The surface of the pipe shall be free from dust,
laitance, oil and water.
Ø The core cut shall be free from debris, dust or any
foreign materials.
Ø Bath seal tape need to be unrolled to required length and
wrap around the pipe by removing release film from one side of the tape.
Ø The length of the tape shall be taken in such a way that
the overlap of tape maintains to be 150mm.
Ø Pipe need to be inserted with Bathseal tape or equivalent
wrapped into the core and support it with formwork from below the slab or
support from the periphery of the wall so that the gap around the pipe and the
core shall be uniform throughout.
Ø The bore packing shall be done with Non-shrink free flow
cementitious grout, , so that there is no air entrapment / voids creating
STEP- 3:
APPLICATION OF TWO PART COMPONENT ACRYLIC POLYMER BASED CEMENTITIOUS
COATING
Ø Top level of the waterproofing shall be marked.
Ø The entire surface to be coated must be in SSD condition
prior to application of coating acrylic polymer based cementitious coating as
per approved brand.
Ø Mixing: Using a slow speed mechanical mixer and a clean suitable
mixing vessel, slowly add the powder component to the liquid polymer and stir
until a smooth and homogenous slurry is achieved.
Ø Allow the mixed slurry to stand for 5 – 10 minutes to
remove air bobble created during mixing.
Ø Do not dilute with water during or after mixing.
Ø Apply mixed cementitious slurry by brush or roller.
Ø Allow the first coat to dry completely for 6 – 8 hours
before applying the second coat.
Ø Apply second coat at right angles to the first coat.
Ø Coating to be applied as per recommendation of manufacturer
regarding application tool.
Ø Allow the coating to cure for 3 – 4 days before
application of protection layer.
Ø Cure the applied cementitious slurry for period of 7 to
10 days. Or minimum of 3 to 5days if further activities starts immediately.
STEP-
4 : PROTECTION OF COATED SURFACE
A.
Protection to waterproof coating (Horizontal Surface)
Ø Cement sand mortar to be laid for protection to the
coating laid to slope to the drainage point.
Ø This mortar shall be minimum 30 to 40mm thick and shall
admixed with integral waterproofing compound as per approved brand.
Ø Cement mortar for base coat shall be used minimum ratio
of 1:4
Ø Curing shall be done at least for 7 to 10 days.
B.
Protection to waterproof coating (Vertical
Surface)
Ø After chemical coat, a rash coat shall be applied for
better bonding with cementitious mortar bedding.
Ø Protection Layer or base coat will be carried out.
Ø This mortar shall be minimum 15 to 20mm thick and shall
admixed with integral waterproofing compound as per approved brand.
Ø Cement mortar for base coat shall be used ratio of 1:4 .
Ø Top of base coat shall be trowel finish to receive the
block / brick bat upto required level.
Ø Curing shall be done at least for 7 to 10 days.
STEP-
4 : BRICK BAT COBA FOR FILLING OF SUNKEN AREA or TERRACE SLAB;
Ø Level pad shall be prepared as per the required slop
towards nahani trap as per drawing or specification.
Ø Bricks selected for using as brick bat coba shall be
either full brick or ¾ brick made out of one complete brick by breaking into
required sizes using mallets.
Ø Brick bat shall be soaked thoroughly for about 15 minutes
prior to their placing.
Ø A thin layer of cement slurry shall be laid on cleaned
slab prior to laying of brick bats, cleaning to be ensured before laying the
brick bat.
Ø On applied cement surry, 10 to 20mm thick layer of cement
sand mortar in the proportion 1:4 mixed with compatible waterproofing compound
shall be laid.
Ø Approved integral waterproofing admixture shall be mixed
with cement mortar as per data sheet.
Ø Mortar shall be mixed properly and same shall be used
within 60 minutes from its mixing time.
Ø Broken brick bats of required size shall be placed over
the cement mortar bed by hand packing having minimum 15 to 20mm gap between
broken bricks.
Ø Pre-soaked brick bats shall be laid in radial by
inserting brick bat s to a depth of about 10mm by light tamping.
Ø Mortar shall be ratio of 1:4 shall be used for filling of
gaps between broken bricks.
Ø Cement mortar shall be filled up to 2/3rd height of the
broken bricks.
Ø Laying of brick bats should proceed from one corner and
shall be laid in radial pattern to drain off any water which has seeped through.
Ø Thiyyas / Level Pad for the same shall be given by
operation engineer, Brick bat shall be laid accordingly.
Ø Brick bat each layer will be cured for minimum 3 days
Ø Post Curing, remaining 1/3rd height filling of brick bat
and 20mm thick cement mortar screed / cement mortar plaster shall be provided
in a single layer.
Ø Sand mortar in the proportion 1:4 with waterproofing
compound (as per mix ratio)
Ø Top coat shall be of neat cement slurry of adequate
consistency and shall be monolithic with brick bat.
Ø Waterproofing plaster shall be extended upto 500 mm (from
RCC slab Top) on vertical surface/ parapet wall.
Ø Average thickness of brick bat coba shall be maintained
as per project specification.
Ø Top level shall be maintained as per drawing & slope.
Ø Pond Curing shall be done for 7days and leakage shall be
checked.