Pages

METHODOLOGY / PROCEDURE OF ALUMINIUM SHUTTERING / MIVAN SHUTTERING & CONCRETING


METHODOLOGY/ PROCEDURE OF 
ALUMINIUM SHUTTERING AND CONCRETING


1.   ALUMINIUM SHUTTERING COMPONENTS

 

 WALL COMPONENTS:

a) Wall Panel: - It forms the face of the wall. It is an Aluminum sheet properly cut to fit the exact size of the wall.

                                

                                                                 WALL PANEL

 b) Rocker: - It is a supporting component of wall. It is L-shaped panel having allotment holes for stub pin.

                       

                            ROCKER

c) Kicker: - It forms the wall face at the top of the panels and acts as a ledge to support.

                                                                                                                              KICKER 

d) Stub Pin: - It helps in joining two wall panels. It helps in joining two joints.

                                      

 STUB PIN 

e) Wall Tie: - - It helps in joining two parallel wall panels and it helps to maintain the spacing of walls.

                                                                                                

WALL TIE

5.2. BEAM COMPONENTS:

a) Beam Side Panel: - It forms the side of the beams. It is a rectangular structure and is cut   according to the size of the beam.

                          

 BEAM SIDE PANEL

b) Prop Head for Soffit Beam: - It forms the soffit beam. It is a V-shaped head for easy dislodging of the formwork.

           PROP HEAD FOR SOFFIT BEAM.

 

 

c) Beam Soffit Panel: - It supports the soffit beam. It is a plain rectangular structure of aluminum.

                         

   BEAM SOFFIT-PANEL  

d) Beam Soffit Bulkhead: - It is the bulkhead for beam. It carries most of the bulk load.

                         

 BEAM SOFFIT BULKHEAD

5.3.  DECK COMPONENT:

a) Deck Panel: - It forms the horizontal surface for casting of slabs. It is built   for proper safety      of workers.

 

    DECK PANEL

b) Deck Prop: - It forms a V-shaped prop head. It supports the deck and bears the load coming   on the deck panel.

                                     

DECK PROP 

 

 

c) Prop Length: - It is the length of the prop. It depends upon the length of the slab.

                                      

  DECK PROP LENGTH

d)  Deck mid – Beam: - It supports the middle portion of the beam. It holds the concrete. 

                       


     DECK MID-BEAM

e) Soffit Length: - It provides support to the edge of the deck panels at their perimeter of the room.

 

 SOFFIT LENGTH

f)  Deck Beam Bar: - It is the deck for the beam. This component supports the deck and beam.

                            

   DECK BEAM BAR

 5.4. OTHER COMPONENTS:

a) Internal Soffit Corner: - It forms the vertical internal corner between the walls and the beams, slabs, and the horizontal internal cornice between the walls and the beam slabs and the beam soffit.

           

 INTERNAL SOFFIT CORNER

 

b) External Soffit Corner: - The external soffit corners forms the vertical external corner between walls and / or beam faces and horizontal external corners between wall / beam face and soffit of slabs.

  

EXTERNAL SOFFIT CORNER

c) External Corner: - The external corner connects vertical or horizontal form work together at right angles.

EXTERNAL CORNER 

d) Internal Corner: - It connects two pieces of vertical formwork pieces at their internal intersections.

   

 INTERNAL CORNERS

 

5.5. FORMWORKS ASSEMBLE:

 

a)     WALL ASSEMBLY DETAILS

 

 FIG:- WALL ASSEMBLY DETAILS

 

 

 

 

b)    BEAM & DECK PANEL ASSEMBLY DETAILS 

 

              FIG: - BEAM & DECK PANEL ASSEMBLY DETAILS

 

 

METHODOLOGY FOR FORM WORK

 

6.1            DESIGN CONCEPT

During the designs of form work the following points shall be considered:-

Ø Unit weight of concrete

Ø Type of structure

Ø Rate of pouring of concrete

Ø Pouring sequence of concrete

Ø Tolerance of deflection

Ø Vertical and lateral load including live and vibrating loading.

The design calculation and drawing for the different structure like slab, beam, column, retaining wall etc. shall be made by in-house form work departments. The same calculation and drawings shall be submitted to the client for information / Records / Approvals.

6.2. CONSTRUCTION ACTIVITIES WITH ALUMUNNNIUM SHUTTERING AS FORMWORK;

 

The construction activities are divided as Pre Concrete activities, During Concreting and Post Concrete activities. They are as follows:

 

       6.2. A.  PRE-CONCRETE ACTIVITIES:

 

i)        RECEIPT OF MATERIALS  ON SITE:

Ø Unload components from transport and where possible, stack by code and size panels can normally be stacked safely up to 25 panels high on skids or pallets.

Ø When stacked, hole in the formwork should be aligned allowing easy   identification by code.

Ø Ensure the first panel at the bottom of the stack has the contact face upwards.

Ø All pins, wedges, wall ties, sleeves, and special tools to be put into proper storage.

Ø Check to be carried out against the packing list ensuring all items stated are received.

 

ii)       LEVEL SURVEYS:

Ø A concrete level survey should be taken on all sites and remedial work carried out prior to the erecting of formwork.

Ø All level surveys should be taken from T.B.M (Temporary Bench Mark).

Ø High spots along the wall line to be chipped off to the proper level. Low spots along the wall line should be packed to the required level, using plywood or timber.

Ø Packing the corner and the Centre of the wall length to the required level will be normally be adequate, as the formwork when pinned together will bridge across low spots.

Ø Concrete (+10mm) and above must be chipped to the correct level. 

Ø After concreting, level surveys should also be carried out on the top of the kickers.

Ø Kickers are manufactured with a 26mm slotted hole on the face to allow for adjustment after concreting.

 

iii)      SETTING OUT:

Ø Only approved shell drawings supplied by Formwork Design will be used for setting out.

Ø Setting out lines will continue through openings, external corners etc., by a minimum of 150mm. This makes it easier to fix formwork in position prior to concreting.

Ø The reference points and the setting out points will be protected against accidental movement or damage.

Ø Transferring of reference points from the level below requires to be done quite accurately.

Ø Survey Equipment will be used for transferring the points through openings provided in the slab.

 

iv)  CONTROL/CORRECTING OF DEVIATIONS:

Ø A study of the deviation and kicker level survey will confirm if any corrective action is required.

Ø If the kicker requires adjustment for level, loosen the holding in bolt by turning anti-clockwise, adjust kicker to the required position and retighten the bolt.

Ø Once the vertical formwork is fixed in position, the external corners will be checked for plumbness. This will determine if further action is required to control the deviation.

Ø In addition to the kicker levels, the formwork can be pulled by using bottle screws and chain blocks; if the formwork requires to be pushed adjustable props can be used.

 

v)       ERECT FORM WORK:

Ø For the initial set up only 50mm*25mm timber stays can be nailed to the concrete slab, close to the internal and external corners, to ensure the formwork is erected to the setting out lines.

Ø All formwork begins at a corner and proceeds from there. This is to provide temporary lateral stability. 

Ø A single panel at a corner will give sufficient lateral support to a very long section of wall.

Ø Ensure all edges of the formwork and contact face are properly cleaned ad oiled prior to fixing in place.

Ø When satisfied the corner is stable and the internal corner is positioned to the setting out lines continue erecting the formwork to one wall.

Ø Initially only 2 no of pins and wedges will be used to connect the formwork at this stage the pins and wedges will have to be removed later to insert the wall ties.

Ø Alternatively the wall ties can be positioned as the formwork is erected.

Ø For ease of striping, pin the wall panels to the internal corners with the head of pin to the inside of the internal corner if possible.

Ø Wall ties will be coated with the approved releasing agent provided before fixing to the formwork.

Ø Fit the wall ties through slots in the wall formwork and secure in position with pins and wedges.

Ø Prior to closing the formwork, pre-wrapped corrugated PVC sleeves are placed over the wall ties.

Ø Sleeves installed with one end fixed between the side rails of two adjoining panels, exposes the wall tie at the opposite end, therefore impossible to retrieve the wall tie after concreting.

Ø If any deviation of external walls occurs, wall will be brought back to the correct plan location as quickly as possible. This is done by slightly tilting the external wall forms in one plane.

Ø If any deviation from plumb has occurred in two directions, then this will be improved over two floors, one for each direction. Realignment in two directions will not be attempted on a single lift.

Ø A maximum of 10mm in vertically improvement in one lift is sufficient.

 

vi)       METHOD OF ERECTING FORMWORK:

 

Ø One side is erected using only on upper and lower pin and wedge connection. Later, ties are inserted at the connection and fixing with pin and wedge.

Ø Then previously installed pins are removed and those ties inserted and pinned. Subsequently, panels for the other side are inserted between the existing ties and fixed with pins and wedges.

 

 

 

The advantages of this Erection Method are as Follows:-

Ø Rooms can be closed and squared by assembling only one side of wall panels. If misaligned, it is easier to shift rows of single panels.

Ø If steel reinforcement is likely to interfere with the placement of the ties, it can be seen and corrected without delaying the pane erection.

Ø Enables fast start up of deck teams as the first rooms can be closed quickly.

Ø Continuous steel reinforcement for the walls creates a barrier between the two sides of the formwork, so the work proceeds at the pace of single erector.

 

Special care must be taken at the lift shafts as Follows:-

Ø The interior panels will align properly on their own because they are set of the kicker from the formwork below.

Ø Ensure the kickers are level and will not affect the vertically of the lift shaft. However, the matching panels are set on the concrete that may not be level.

Ø The ends of walls and door openings will be secured in position by nailing timber stays to the concrete slab.

Ø Walls require to be straightened by using a string line and securing in place by nailing timber stays to concrete slab.

Ø Vertically of door openings also to be checked for plumb.

 

vii) ERECT DECK FORMWORK:

Ø Normally deck panels can be struck after 72 hours.

(Striking times should be confirmed by Client / Consultant).

Ø The striking begins with the removal of deck beam. Remove the 132mm pin and the beam bars from the beam which has been identified for removal.

Ø This is followed by removing the pins and wedges from the deck panels adjacent to the deck beam to be removed.

Ø The deck beam can now be taken out.

Ø As the first panel in are rests on the support lip of the soffit length, the adjacent panel will be removed first.

Ø After removing the pins and wedges from the panel to be removed, a panel puller can be used to beak the bond from the adjacent formwork.

Ø Where there is no deck beam support and the panels span from wall to wall, one wall will have the supporting lip of the soffit length removed.

Ø Pins and wedges only to be removed on the identified component that is to be struck.

Ø Deck panels remains in place longer than wall panels and will not come away easily unless proper cleaning and oiling is done during the erection process. Panels should confirm to the sequence of erection.

 

Vii) PROP LENGTHS (PL):

Whenever the PL's is to be removed, wooden mallet will be used to strike the bottom of the PL in the same direction as the beam and holding the PL with other hand.

 

6.2. B. DURING CONCRETE ACTIVITIES:

 

At least one supervisor & two Skilled Carpenters will be on standby during concreting for checking pins, wedges and wall ties as the pour is in progress. Pins, wedges or wall ties missing could lead to a movement of the formwork and possibility of the formwork being damaged. This effected area will then require remedial work after striking of the formwork.

 

Things to look for during concreting;

            i. Dislodging of pins / wedges due to vibration.

            ii. Beam / deck props adjacent to drop areas slipping due to vibration.

            iii. Ensure all bracing at special areas slipping due to vibration.

            iv. Overspill of concrete at window opening etc.

 

6.2. C. POST CONCRETE ACTIVITIES: 

 

i)  CLEANING:

All components should be cleaned with scrapers and wire brushes as soon as they are struck.

Wire brush is to be used on side rails only.

The longer cleaning is delayed, the more difficult the task will be. It is usually best to clean panels in the area where they are struck.

 

 

 ii)  Transporting:

There are basic three methods recommended when transporting to the next floor:

a. The heaviest and the longest, which is a full height wall panel, can be carried up the nearest stairway.

                         b. Passes through void areas.

c. Rose through slots specially formed in the floor slab for this purpose. Once they have served their purpose they are closed by casting in concrete filter.

 

iii)  Striking:

Once cleaned and transported to the next point of erection, panels should be stacked at right place and in right order.

Proper stacking is a clean sign of a wall – managed operation greatly aids the next sequence of erection as well as prevents clutters and impend other activities.

 

INSTRUCTIONS:

 

To be imposed on every worker, are the following things not to be done:

Ø Do not lay bottom panel contact face down, when starting a stack

Ø Do not drop equipment from any height

Ø Do not use panels as ramp, bridges or scaffold

Ø Do not use hammer and wedges to pull panels together

Ø Do not drive wedges until full length of panels are butted together

Ø Do not use extreme hammer force when installing wedges

Ø Do not erect elements which are not properly cleaned and oiled

(Deck panel faces are oiled after erection)

 

6.3.     STRIPPING TIME

It is the minimum time before which formwork of freshly laid concrete structure should not be removed. It depends on various factors like ambient temperature, type of cement, type of structure etc. For ambient temperature of more than 150C and concrete made with OPC cement and crushed stone aggregate stripping time may be followed as a general guideline as per Clause 11.3 of IS: 456-2000.

Sr. No:

Description

Stripping Time

1

Vertical formwork for Cols, walls and sides of beams

16 to 24 hours

2

Slabs ( Props Remaining )

3 days

(Subject to 3days cube results )

3

Beam soffit( Props remaining )

7 days

4

Removal of props to slabs:

 

 

a. Spanning up to 4.5 m

7 days

 

b. Spanning over to 4.5 m

14 days

5

Removal of props to beam and arches

 

 

a. Spanning up to 6.0 m

14 days

 

b. Spanning over 6.0 m

21 days

 

 

Note: Deshuttering of panels can be started after achieving 10Mpa compressive strength of concrete. Reproping should be maintained.

Or. Formwork removal will be based on 3days cube strength.

 

 

 

6.4.   PROPING AND REPROPING:







Slab to be Casted (N)

 i.           100 % Props as per Drawing @ N- 1 

ii.         70 % Props remaining @ N- 2 

iii.         30 % Props remaining @ N- 3 

 


 


6.5.       TOLERANCES

Tolerances are the specified permissible variation from lines, grade or dimensions given in the drawings. Unless otherwise specified, the following tolerances will be permitted:

Sr. No.

DESCRIPTION

PERMISSIBLE DEVIATIONS

1

Deviation from specified dimension of cross section of column and beams

-6 mm

+12 mm

2

Deviation from dimension of footing.

± 10 mm

a)

Dimension in plan

-12 mm

+50 mm

b)

Eccentricity

0.02 times the width of footing in the direction of deviation but not more than 50 mm.

c)

Thickness

± 0.05 times specified thickness.

3

Departure from level shown on the drawing.

± 6 mm

4

Deviations

Abrupt irregularities/offsets caused by displaced or misplaced formwork lining or supports.

±10 mm

5

Inserts

Variation in position along concrete surface

In plane position (flush with concrete face)

± 10 mm

 

± 5 mm

 

Note: Tolerance may be change based on project specification.



2.   WORK METHODOLOGY FOR CONCRETING OF ALUFOM SHUTTERING

1.           ACTIVITIES BEFORE CONCRETING

 

Ø  All formwork activities will be carried out in accordance with the specification & drawings, structural reinforcement work will commence once formwork is completed above 50% of plane area. MEP sleeves in beams & insert plates can be started before starting beam side formwork.

Ø Lay the main reinforcement bars of bottom layer of the slab spaced evenly according to design or drawings, once sufficient progress (around 50% area) is achieved in slab reinforcement bottom layer, parallel MEP activities like electrical conduiting, insert plates, MEP sleeves, MEP cut outs are started from bottom layer completed end to work in progress end, so as there will be synchronization between civil & MEP activities.  

Ø Install bar chairs acting as spacers between top and bottom reinforcements.

Ø Lay the top reinforcements with distribution bars fixed on first and the main reinforcements on the upper layer (transverse direction).

Ø After completing the slab top reinforcements, clean and blow away the dust by using compressed air/hand held blowers.

Ø Meantime, the surveyor must check the formwork level and install the markings for the concrete level using auto level instrument & leveling staff.

Ø After the formwork level measurements are done, furnish the copy from the surveyor and locate the area which varies from the correct level.

Ø After the adjustment is done, do a routine formwork inspection to check the stability of the frames and runners.

Ø Ensure the slab level markers are fixed nice and tight so that it will not move during the concrete pouring operation.

Ø Check all the formwork gaps and ensure that they are plugged before concrete placement. Concrete slurry will flow through the gaps and will lead to grout loss if not rectified.

Ø Spray water to the formwork and reinforcements to lower down the temperature.

Ø Prepare the vibrator machine / check its availability while waiting for the concrete truck to come. It is always good to have a back-up vibrator if in case something goes wrong, so we have Diesel operated vibrator in addition to electrical high frequency vibrator.

     

 Concrete Mix Proportion

     Ã˜ The Mix Design shall be established for various grade of concrete to determine                     proportion of cement, aggregate, water and Admixtures to attain the required strength shall     be either preparation of design Mix.

    Ã˜ For Design Mix concrete proportion of raw material shall be finalized as per IS 10262         “Recommended guidelines for concrete mix design”.

Ø  Minimum Cement content, Water cement ratio shall be followed as per specification & IS standards.

Ø The compliance of a design mix for structural concrete shall be judged by the strength of hardened concrete in comparison with the specified characteristic strength.

Ø Final Mix design of concrete shall be submitted to for approval from client.

 

7.2       Batching of Concrete.

 

Ø  Availability of all approved material shall be ensured by approved RMC Vendor.

Ø  In proportioning concrete, the quantity of both cement and aggregate shall be determined by weight and as per approved Mix Design.

Ø  The water-cement ratio shall be maintained as a constant at its correct value. As per approved Mix design

Ø  Determination of moisture content in both fine and coarse aggregate shall be done on daily basis for required water correction.

Ø  The concrete shall be thoroughly mixed to achieve required workability at the point of pouring.

Ø  Approved admixture shall be used in required quantity to achieve workability and longer setting time. Dosage shall be as per approved Mix Design.

7.3   Transportation

 

Ø  Concrete transportation shall be done by Transit Mixer from batching plant to the point of place to ensure that there shall not be any segregation.

Ø   With every load of concrete delivery slip (Batch Sheet) shall be issued mentioning dispatch date & time, Grade of Concrete, Location, Quantity, Slump & Temperature of concrete.

Ø  Concrete shall be transported from the mixer to the formwork as rapidly as possible by    methods that will prevent the segregation, loss of any ingredients

or ingress of foreign matter or water and will maintain the required workability.

Ø   Concrete shall be deposited as close as possible to its final position to avoid segregation & re-handling of the concrete.

 

7.4    Placement & Compaction of Concrete.

 

Ø  Concrete Pour shall be commenced after getting approval (Pour card) as per approved ITP.

Ø  Before placing concrete, all equipment for mixing and transporting the concrete shall be cleaned.

Ø  he face of construction joint shall be roughened and all loose material shall be removed & approved  bonding agent shall be applied prior to concrete.

Ø  Sweet water shall be sprinkled on soil, PCC, shutter prior to concrete.

Ø  Concrete shall be placed as nearly as practicable in its final position to avoid segregation due to re-handling or flowing.

Ø  Concrete shall be placed while it is sufficiently workable for full compaction. It shall be worked around reinforcements and embedded items.

Ø  The Concrete Shall be Placed and compacted before initial setting of concrete.

Ø  Free fall of concrete shall not be more than 2.0 m or as per IS code guideline.

Ø  Chutes, hopper gates & other points of discharge shall be so designed or fitted with suitable baffles that concrete passing from them will not segregate during its free fall into place.

Ø  As concrete is placed, it shall be adequately vibrated with internal vibrators to the point of consolidating into a dense homogeneous mass thoroughly embedding the reinforcement and filling all corners and angles.

Ø  Concrete shall not be moved horizontally by vibration. (Vibration will be in controlled manners)

Ø  Concrete shall be properly worked around the reinforcement, the embedded fixtures and into the corners of formwork, so as to achieve finished surface of concrete.

 

7.5      Finishing & Curing

 

Ø   All exposed concrete surfaces shall be left reasonably smooth and free of excessive form marks and honeycombing.

Ø   Top surfaces of concrete in walls, beams and floors shall be finished to the proper level. No holes or rough patches shall remain.

Ø  Newly placed concrete shall kept wet by the continuous application of water for the first 7 days.

Ø  Casting date shall be marked on all concrete elements for having track of curing period.

Ø   All vertical faces shall be covered with Hessian cloth and kept wet.

Ø  For Horizontal surface like slab, foundation etc. shall be cured by ponding water.

Ø  Curing compound shall also be used after prior approval and shall be immediately applied after de-shuttering of the concrete element.

Ø  Proper Construction joint shall be provided for the further lift.

Ø  For construction joint shear key shall be provided throughout length of wall, at center of column & foundation.

Ø  Construction joint in slab & beam shall not be at center of its span it should be at 1/3rd length of span and should be vertical as per consultant or Client approval.

 

7.6      Precautions to avoid Cracks in Mass Concrete

 

Ø  Plant mixed concrete shall have a temperature between 5 deg. C to 40 deg. C.

Ø   Thickness of freshly laid concrete layer shall not exceed 450 mm.

Ø   Good compaction of the concrete shall be secured. Slump of concrete shall be maintained to the minimum possible to avoid possible shrinkage cracks.

Ø  Mass concrete shall be protected from excessive heating and premature drying by covering it with wet hessian cloth, as soon as the concrete gets a set, enough to avoid disturbance of finished surface.

Ø   Curing shall be done for a minimum period of seven days.

 

7.7      Inspection & Testing 

 

Ø  Testing shall include compressive tests of molded concrete cubes and slump tests for consistency, according to IS 516 & IS 1199.

Ø   For Sampling of Compressive Testing set (6 Specimen) of cubes shall be prepared, which include 3 specimens each for 7 days & 28 days as per IS 456.

Ø   The fresh concrete shall be sampled in accordance with IS 1199.

Ø   Rate of sampling shall be as per project specification.

Ø   Slump test shall be carried out to check the consistency of concrete.

Ø  Inspection shall be carried out as approved ITP and Acceptance criteria shall be as per applicable codes and specification.

 

                                                    =    *    =

No comments:

Post a Comment