WORK METHODOLOGY / PROCEDURE INTERNAL
PAINTING;
Surface
Preparation
Ø
For working at height, fixed and movable scaffolding
would be erected as per area requirements.
Ø
Scaffolding when erected shall be inspected with Safety
officer prior to usage.
Ø
Hardware materials which are already fixed and not to be
painted shall be removed.
Ø
Removal if not possible, it shall be covered/protected
appropriately before surface preparation and painting will commence.
Ø
Al items which are not part of structure will be removed
and repaired before painting.
Ø
Clean and prepare plaster surfaces to be painted.
Ø
All major surface cracks of gypsum surface shall be
filled up with acrylic putty before start of putty or painting activities.
Ø
Efflorescence, chalk, dust, dirt, grease and oils shall
be removed by using of sanding or scraping.
Ø
The surface of the area to be painted would be prepared
by removing loose particles, blemishes and deleterious materials by way of
sanding or scraping.
Ø
All clearance will be taken from both civil & MEP
team before initiating the activities. So that, any other activities should not
be executed after painting.
Application
of Putty / Primer
Ø
Proper scraping with sand paper no. 60 shall be done on
gypsum surface.
Ø
One coat of primer shall be applied before 24hrs of application
of putty by using of roller brush.
Ø
Primer shall not be applied on gypsum surface in case of
using Acrylic putty 2X or equivalent.
Ø
Putty shall be applied at least after 6 to 8hrs of
application of primer in case of primer is required or as per manufacturer
guideline.
Ø
Approved Water based Ready to use acrylic putty shall be
applied uniformly by using of flat bladed plate or large putty knives with one in
each hand.
Ø
Applied putty shall be allowed to dry at least for 16 to
24 hrs. or as per technical data sheet.
Ø
After drying of first coat of putty, surface shall be
smoothened by using sand paper (sand paper no shall be as per paint manufacture’s
guideline).
Ø
Then Second coat putty shall be applied after smoothening
of first coat of putty like the first coat.
Ø
Once the second coat is fully applied and has dried
thoroughly, the entire wall shall be smoothening with fine sand paper no
220/320 before painting or as per manufacturer guideline.
Ø
After rubbing with
sand paper, surface putty dust shall be wiped off with a cloth or sponge.
Ø
Cleaning of MEP items, Door and other items shall be
done.
Application of Paint
Ø
The surface to be painted shall be free from any loose
paint, dust and oil & grease.
Ø
Any visible surface cracks shall be repaired prior to
start of painting.
Ø
Approved paint types shall be used. It may be OBD or acrylic
or semi acrylic type.
Ø
Then two coats of final paint shall be applied as per the
approved RAL colour code.
Ø
Paint shall be applied by using of roller brush.
Ø
Applied first coat paint shall be allowed to dry at least
for 3 to 4 hrs or as per technical data sheet.
Ø
After drying of first coat of paint Second coat paint
shall be applied.
Ø
For removal of any surface stain or wipe cleaning shall
be done minimum after 15 days of paint application.
Ø
Second / Final coat paint shall be applied after completion
of all activities.
Ø
Cleaning of MEP items, Door and other items shall be
done.
Before making bulk purchases, it’s wise to compare the hdpe sheet price per kg from verified manufacturers. The rate can differ based on density, thickness, and quality standards. HDPE sheets are ideal for water tanks, chemical containers, and industrial flooring. Investing in quality material ensures better impact strength and long-term performance, making it a cost-effective choice for multiple sectors.