METHODOLOGY / PROCEDURE OF INSTALLATION OF MS RAILING

WORK METHODOLOGY / PROCEDURE OF 

INSTALLATION OF MS RAILING


a.  BALCONY RAILING

Ø  Grade & size of the MS steel shall be finalized prior to start of activities.

Ø  The position & marking of vertical & horizontal level shall be marked on wall as per drawing.

Ø  The structural steel shall be free from the defect and shall have a smooth finish.

Ø  The materials shall be free from loose mill scale, ruts pits or other defects affecting the strength and durability

Ø  The structural member shall be installed with required scaffolding if required.

Ø  Necessary bolting or welding shall be done as per drawing. Anchor bolts shall be fitted as per structural details (if applicable).

Ø  The joints between horizontal & vertical structural member shall be done as per Architect / structural engineer in charge.

Ø  Dimension of the structural shall be checked as per drawing prior to start erection.

Ø  The erection of whole structure shall be done properly to maintain line, level and plumb.

Ø  Fabricating and installing shall be done as per drawing and design.

Ø  The height of the railing shall be considered from the respective finished floor level as per drawing.

Ø  M.S box pipe shall be used as main vertical members and handrails or as per drawing requirement.

Ø  Intermediate vertical MS plate / Strip shall be provided as per drawing.

Ø  Joint preparation shall be done properly prior to start of jointing.

Ø  Finishing of railings shall be shall be done by applying one coat primer and two coats of oil paints etc. or as per recommendation of architect / structural engineer in charge.

Ø  Coating and painting will be done as per specifications.

 

 

b.  STAIRCASE RAILING

 

Ø  Grade & size of the MS steel shall be finalized prior to start of activities.

Ø  The position & marking of vertical & horizontal level shall be marked on the staircase wall as per drawing.

Ø  The position of vertical posts shall be marked as per drawing.

Ø  The structural steel shall be free from the defect and shall have a smooth finish.

Ø  The materials shall be free from loose mill scale, ruts pits or other defects affecting the strength and durability

Ø  The structural member shall be installed with required scaffolding as per sire requirements.

Ø  Necessary bolting or welding shall be done as per drawing and specification. Anchor bolts shall be fitted as per structural details (if applicable).

Ø  The joints between horizontal & vertical structural member shall be done as per Architect / structural engineer.

Ø  Dimension of the structural shall be checked as per drawing prior to start erection.

Ø  The erection of whole structure shall be done properly to maintain line, level and plumb.

Ø  Fabricating and installing shall be done as per drawing and design.

Ø  The height of the railing shall be considered from the respective finished floor level.

Ø  Size of M.S pipe for vertical members and handrails shall be as per approved drawing.

Ø  Intermediate supports parallel to the handrail at given distances as per drawing.

Ø  Intermediate vertical members shall be provided as per approved drawing.

Ø  Base of the vertical posts shall be fixed by anchor fastener or welding or as per drawing & specification.

Ø  Finishing of railings shall be done by applying one coat primer and two coats of oil paints etc. or as per recommendation of architect / structural engineer in charge.

Ø  Adequate slope and alignment will be provided as per drawing.

Ø  Diameter and length at structural member will be checked before fixing.

Ø  Painting and coating as per specification.

 

 