METHODOLOGY / PROCEDURE OF WATERPROOFING OF STP / UGT
CONTENT
SL NO | ACTIVITIES | |
1 | INSTALLATION OF HDPE MEMBRANE BELOW RAFT / ABOVE PCC | |
2 | INSTALLATION OF SBS SELF ADHESIVE MEMBRANE ON OUTER SIDE OF RETAINING WALL | |
3 | APPLICATION OF SOLVENT BASED POLYURETHANE (PU) MEMBRANE FOR TERRACE SLAB & CHHAJJA OF STP / UGT | |
4 | WATERPROOFING TREATMENT INSIDE THE STP / UGT |
1. INSTALATION
OF HDPE MEMBRANE BELOW RAFT / ABOVE PCC
STEP-1. SURFACE PREPARATION:
Ø The concrete surface shall be cleaned thoroughly of all
contaminants like dust, traces of curing compound, oil and grease.
Ø All surface imperfections, protrusions, structurally
unsound and friable concrete must be removed and repaired with a suitable
concrete repair mortar.
Ø All surface cracks must be repaired with approved
repairing materials.
Ø All cracks below 5mm shall be cut opened, cleaned and
shall be filled with shrink free crack filling material,
Ø All surface cracks, undulations and voids shall be
repaired appropriately before application.
Ø The entire surface to be coated must be in SSD condition
prior to application of coating.
STEP-2. INSTALATION OF HDPE MEMBRANE:
Ø Film side HDPE membrane to be placed on the PCC substrate
with adhesive (if required )
Ø Sand layer side up facing towards the concrete or Raft
pour
Ø End lapping positioning of HDPE membrane will be done as
per manufacturer's guideline.
Ø It is essential to achieve continuous bond without
creases and with a heavy roller to roll firmly on joint of HDPE membrane.
Ø All the overlaps and end laps to be secured additionally
by applying over the joints in opposite direction with double sided tapes to
ensure watertight joints.
Ø After completion of installation of HDPE membrane,
reinforcement fixing and concreting activities can be started.
Ø Termination of HDPE membrane shall be done on side of
raft, from where SBS membrane will be started.
STEP-3.
FIXING OF PRESSURE RELEASE PIPE (PRP)
Ø Provide Pressure Release Pipe (PRP) and with washed gravels
at the time of laying of PCC.
Ø Galvanized Iron pipes (PRP) of 25mm diameter inside the
pocket 50mm length, 50mm width and 50mm deep need to be provided
Ø The mouth of the
pipes need to be closed with tough plastic cover to avoid blockage of the pipes
from pouring concrete.
Ø The length of the pipe shall be such that it remains
outside the raft level.
Ø Each PRP shall be wrapped and dressed at the PCC top with
Non-shrink grouting material / non-shrink mortar and shall be terminated with
metallic Jubilee clip and PU sealant at joint location.
Ø The Pre-bond HDPE membrane shall be terminated over the
PU flashing.
Ø The PRP shall be hold in position at the time of laying
PCC so that the PRPs remain in vertical position.
Ø The mouth at the top of PRPs shall be covered with tough
plastic cover so that the pipes does not get blocked at the time of concreting,
2.
INSTALATION OF SBS SELF ADHESIVE MEMBRANE ON OUTER SIDE OF RETAINING WALL
STEP-1:
`SURFACE PREPARATION:
Ø Concrete surfaces should be fully cured (minimum 28 days)
prior to application.
Ø The concrete surface shall be cleaned thoroughly of all
contaminants like dust, traces of curing compound, oil and grease.
Ø All surface imperfections, protrusions, structurally
unsound and friable concrete must be removed and repaired with a suitable
concrete repair mortar.
Ø All surface cracks, undulations and voids shall be
repaired appropriately before application.
Ø All cracks above 5mm deep, shall be cut opened, cleaned and shall be
filled with shrink free crack filling material. i.e. GP2 or equivalent.
Ø Filling up of tie rod holes shall be done with non-shrink
cementitious grout i.e. GP2@ or equivalent.
Ø The entire surface to be coated must be in SSD condition
prior to application of coating.
Ø All the construction joints need to be opened and treated
with polymer modified mortar (Cement: sand: SBR Latex) or ready to use modified
mortar.
Ø Injection grout shall be done at all construction joints.
Nozzle shall be fixed @ 500mm centre to centre at all construction joints.
Ø Wall surface shall be cleaned by Compressed air cleaning to
make the surface free of dust, debris, laitance etc. for proper bonding with
RCC surface.
STEP- 3 :
AAPPLICATION OF PRIMER AND SBS MEMBRANE
Ø Solvent based bituminous Primer need to be applied on the
entire surface of RCC wall as per manufacturer guideline.
Ø After priming of RCC surface, approved SBS membrane shall
be installed or fixed on primed surface.
Ø Minimum time gap must be maintained between applying of
primer and fixing of membrane as per manufacturer guideline.
Ø SBS membrane application shall be started from bottom of
the wall.
Ø Lapping of HDPE membrane (Which comes from bottom of the
raft) and SBS membrane shall be done properly as per manufacturer guideline.
Ø Lapping of SBS membrane shall be done as per manufacturer
guideline.
Ø Termination of the SBS membrane shall be done at 200 mm
above the ground level.
Ø Aluminum termination bar shall be fixed at termination
location i.e. minimum 200 mm above Ground level & shall be fixed with
non-corrosive fastener @ 4 nos per rm.
Ø Sealing of termination bar shall be done by applying of
PU Sealant.
Ø The joints of the corners (Internal and external corners)
shall be sealed by returning the membrane a minimum of 100mm and sealing with
Pre-Bond Tape.
STEP- 4 : PROTECTION OF SBS MEMBRANE
Ø Installed SBS membrane shall be protected by using of
11mm thick dimpled board / protection board.
Ø Dimpled board / protection board shall be fixed to avoid
any physical damage of membrane during soil filling.
Ø Fixing of dimple board shall be done as per manufacturer
guideline.
3.
APPLICATION OF SOLVENT BASED
POLYURETHANE (PU) MEMBRANE FOR TERRACE SLAB & CHHAJJA OF STP / UGT
STEP-1:
`SURFACE PREPARATION:
Ø
Ø The surface needs to be clean, dry and sound, free of any
contamination, which may harmfully affect the adhesion of the membrane.
Ø Maximum moisture content should not exceed 5%. Substrate
compressive strength should be at least 25 MPa, cohesive bond strength at least
1.5 MPa.
Ø New concrete structures need to dry for at least 28 days.
Old, loose coatings, dirt, fats, oils, organic substances and dust need to be
removed by a grinding machine. Possible surface irregularities need to be
smoothened.
Ø Any loose surface pieces and grinding dust need to be
thoroughly removed.
Ø WARNING: Do not wash surface with water.
Ø All surface cracks, undulations and voids must be
repaired before application using a suitable repairing material.
Ø Substrates must be surface dry prior to application.
Ø During surface preparation all fittings of drain outlets
work must be completed.
STEP-2 : PRIMING OF RCC SURFACE
Ø Prime absorbent surfaces like concrete, cement screed
with PU Primer and allow the primer to air cure according manufacturer’s
technical instruction.
Ø Allow the primer to cure for 6 – 8 Hrs to tacky condition
STEP-3 : APPLICATION OF PU MEMBRANE
Ø Stir well before using of PU solvent.
Ø Apply the PU solvent onto the primed surface and lay it
out by roller or brush, until all surface is covered.
Ø Airless spraying method can be allowed a considerable
saving of manpower.
Ø After 12-18 hours (not later than 48 hours) apply another
layer of the PU solvent.
Ø For best results, the temperature during application and
cure should be between 5ºC and 35ºC.
Ø Low temperatures retard cure while high temperature speed
up curing. High humidity may affect the final finish.
Ø The coverage shall be maintained at 1.8 Kg/sqm to achieve
Dry Film Thickness of 1.5mm.
Ø The membrane (both the coats) shall be applied over the
angle fillet and shall be extended over the vertical wall (i.e. Parapet wall )
upto height such that it is terminated at 300mm above Finish Floor Level or
Soil Filling Level.
Ø Allow the membrane to air cure for minimum 3 – 4 days
before any activity over it.
Ø Allow the coating to cure for 2 – 3 days.
STEP- 4 : PONDING TEST OF APPLIED PU MEMBRANE
(If required)
Ø
Make bund wall and fill water to pond the area as per the judgement and
allow the water for 72Hrs.
Ø
Remove water after 72 Hrs after inspection. Allow to dry for 24 Hrs.
STEP- 5: PROTECTION OF PU MEMBRANE (HORIZONTAL
SURFACE)
Ø Provide 200 GSM
geotextile membrane over the waterproofing membrane to create a separation
layer as well as protection layer from screeding.
Ø The geotextile layer shall have 100 mm overlap and spot
bonded and shall be extended at the wall up to 100mm above the slab floor.
Ø Lay Concrete screed of minimum M20 grade concrete (RMC)
over the geotextile membrane. 12mm poly-propylene fibers at 0.9Kg/cum may be
added to avoid shrinkage cracks of concrete.
Ø Provide slope of 1:1000 or as recommended by client.
Ø The slope shall be provided in such a way that there is
40mm minimum thickness at the point of drain outlet.
Ø The screed shall be finished rough with broom and in
shape of watta / rounding at the wall and floor junctions.
Ø The screed shall be cured with water for minimum 07 to 10
days.
Ø After the screed is cured remove all the water, cut
joints in screed with grinder of 10mm wide and 25 mm deep to form panels of 4M
X 4M.
Ø Clean the joints with compressed air to make it dust free
and leave it for 1 or 2 days to remove the moisture from the joints.
Ø Pack in backer rod of round cross-section inside the
joint upto 10 mm depth left at top.
Ø This joint shall be applied with PU primer. Allow to dry
for minimum 2 – 3 Hrs to tacky condition. Then fill the joints with PU sealant.
Ø Allow the sealant
to air cure for 2 – 3 days before covering or laying of further tiles / pavers
if applicable.
STEP- 6: PROTECTION OF PU MEMBRANE (FOR
VERTICAL SURFACE SURFACE)
Ø Over the waterproofing membrane apply 2 coats of Epoxy Bonding
Agent conforming to Shear Bond strength as per ASTM C 881.
Ø Sprinkle sand over the primed surface at 2 – 3Kg/sqm when
the bonding agent is wet.
Ø Allow it to dry to form firm key for the plaster.
Ø Lay 15 to 20mm thick plaster in two coats over the prepared
surface of cement sand mortar mixed with integral waterproof compound conforming
to IS 2645-2003.
4.
WATERPROOFING TREATMENT INSIDE THE STP / UGT
STEP-1:
`SURFACE PREPARATION:
Ø Concrete surfaces should be fully cured (minimum 28 days)
prior to application.
Ø The concrete surface shall be cleaned thoroughly of all
contaminants like dust, traces of curing compound, oil and grease.
Ø All surface imperfections, protrusions, structurally
unsound and friable concrete must be removed and repaired with a suitable
concrete repair mortar.
Ø All surface cracks, undulations and voids shall be
repaired appropriately before application.
Ø All cracks above 5mm deep, shall be cut opened, cleaned and shall be
filled with shrink free crack filling material. i.e. GP2 or equivalent.
Ø Filling up of tie rod holes shall be done with non-shrink
cementitious grout i.e. GP2@ or equivalent.
Ø The entire surface to be coated must be in SSD condition
prior to application of coating.
Ø All the construction joints need to be opened and treated
with polymer modified mortar (Cement: sand: SBR Latex) or ready to use modified
mortar.
Ø Injection grout shall be done at all construction joints.
Nozzle shall be fixed @ 500mm centre to centre at all construction joints.
Ø
Wall surface shall be cleaned by Compressed air cleaning to make the
surface free of dust, debris, laitance etc. for proper bonding with RCC
surface.
STEP- 02 : SEALING OF PIPE INLET / OUTLET
DRAINAGE PIPES AND CORE FILLING
Ø The surface of the pipe shall be free from dust,
laitance, oil and water.
Ø The core cut shall be free from debris, dust or any
foreign materials.
Ø Bath seal tape need to be unrolled to required length and
wrap around the pipe by removing release film from one side of the tape.
Ø The length of the tape shall be taken in such a way that
the overlap of tape maintains to be 150mm.
Ø Pipe need to be inserted with Bathseal tape or equivalent
wrapped into the core and support it with formwork from below the slab or
support from the periphery of the wall so that the gap around the pipe and the
core shall be uniform throughout.
Ø The bore packing shall be done with Non-shrink free flow
cementitious grout, , so that there is no air entrapment / voids creating
STEP- 3:
APPLICATION OF TWO PART COMPONENT ACRYLIC POLYMER BASED CEMENTITIOUS
COATING
Ø The entire surface to be coated must be in SSD condition
prior to application of coating acrylic polymer based cementitious coating as
per approved brand.
Ø Mixing: Using a slow speed mechanical mixer and a clean
suitable mixing vessel, slowly add the powder component to the liquid polymer
and stir until a smooth and homogenous slurry is achieved.
Ø Allow the mixed slurry to stand for 5 – 10 minutes to
remove air bobble created during mixing.
Ø Do not dilute with water during or after mixing.
Ø Apply mixed cementitious slurry by brush, roller.
Ø Allow the first coat to dry completely for 6 – 8 hours
before applying the second coat.
Ø Apply second coat at right angles to the first coat.
Ø Coating to be applied as per recommendation of manufacturer
regarding application tool.
Ø Allow the coating to cure for 3 – 4 days before
application of protection layer.
Ø Cure the applied cementitious slurry for period of 7 to
10 days. Or minimum of 3 to 5days if further activities starts immediately.
STEP-
4 : PROTECTION OF COATED SURFACE
A.
Protection to waterproof coating (Horizontal Surface)
Ø Cement sand mortar to be laid for protection to the
coating laid to slope to the drainage point.
Ø This mortar shall be minimum 30 to 40mm thick and shall
admixed with integral waterproofing compound as per approved brand.
Ø Cement mortar for base coat shall be used minimum ratio
of 1:4
Ø Curing shall be done at least for 7 to 10 days.
B.
Protection to waterproof coating (Vertical
Surface)
Ø After chemical coat, a rash coat shall be applied for
better bonding with cementitious mortar bedding.
Ø Protection Layer or base coat will be carried out.
Ø This mortar shall be minimum 15 to 20mm thick and shall
admixed with integral waterproofing compound as per approved brand.
Ø Cement mortar for base coat shall be used ratio of 1:4 .
Ø Top of base coat shall be trowel finish to receive the
block / brick bat upto required level.
Ø Curing shall be done at least for 7 to 10 days.
hi
ReplyDeleteNice Blog! Get the best roof waterproofing in Mohali at a reasonable price. Our Company provides service to protect your roof by closing cracks and holes to make your structure leakage proof. Get expert waterproofing solutions from our professional team. Reliable roof waterproofing service at a cheap price.
ReplyDeleteNice Blog! Are you searching for a waterproofing company in Baddi? Our team provides waterproofing services in both commercial and residential areas. We protect houses and buildings from leakage.
ReplyDeleteNice Blog! We provide top-quality terrace waterproofing in Derabassi. Get 100% customer satisfaction with our waterproofing services. Our company provides top-quality waterproofing services in both commercial and residential areas.
ReplyDeleteNice Blog! Are you searching for waterproofing services in Mohali? We provide the top quality waterproofing services at a reasonable price. We provide 100% solution and 24*7 available to our customer. Our company has an expert and professional team for waterproofing work. Get 100% customer’s satisfaction on 10 warranty with waterproofing services. Our well qualified team provides modern machine and technology for waterproofing work.
ReplyDeleteNice Blog! Are you looking for terrace waterproofing in Panchkula? We provide top-quality waterproofing services at a reasonable price. We provide customer satisfaction with our waterproofing services. We provide 100% permanent solutions for terraces and 24*7 available for our customers. Our well-qualified team uses different methods and technology for waterproofing work.
ReplyDeleteImpressive blog! Very nice information is given about the waterproofing but to know some more than click on the link Waterproofing in Mohali We are expert in giving the 100% customer satisfaction from our Waterproofing work.
ReplyDelete