WORK METHODOLOGY / PROCEDURE OF INSTALLATION OF
FALSE
CEILING:
Ø Firstly, all required measurements of ceiling (length and
width) and ceiling to wall (for height of false ceiling) shall be taken for
each room where false ceiling is to be installed.
Ø Material Requirement shall be calculated depending on
size i.e. area of rooms where it needs to be installed as per drawing
dimention.
Ø The ceiling levelling shall be marked with water tube.
The ceiling needs to be in one level for correct installation of false ceiling.
Ø After levelling procedure and marking is complete, marking
shall be done on ceiling at distance as per drawing.
Ø Marking shall be also done in side walls at the height
where the false ceiling will be suspended below the original ceiling.
Ø Hooks of metal ceiling angle strip shall be fixed to the
ceiling. These fittings become the chief support points of false ceiling.
Ø For framing, perimeter channels shall be fitted on the
walls at a height where false ceiling will be suspended.
Ø The perimeter channels and free end of hooks shall be connected
with other channels.
Ø This arrangement becomes the fixed section of false
ceiling that acts as the main foundation of false ceiling.
Ø To hang or support False ceiling from main ceiling,
Anchor fasteners if required shall be used. Anchor fasteners provide support to
secondary ceiling.
Ø Sufficient anchorage shall be provided it straight.
Ø Ceiling sections are then fitted to the main foundation
forming much précised framing that enables attaching ceiling board or any other
material used for false ceiling.
Ø The section joints created shall be connected by using
clips that offer strong and durable joints. These connecting clips also help
for easy installations of ceiling board.
Ø Once the framing is completed, wiring for lights, fan and other necessary electrical work shall be completed.
Ø Ceiling Board of approved thickness shall be attached to the framework with help of drywall screws.
Ø The joints and
edges shall be covered and finished
by using of jointing compound and paper tape or as recommended by client
(if required).
Ø Once the finishing process is over, MEP team shall be called to install light fittings and any other fittings
to do final wiring and other electrical work.
Ø The ceiling is now ready to be painted (in case of gypsum ceiling board).
Ø All the diagrams will be obtained at each stage.
Same procedure shall be followed for metal ceiling also.