WORK METHODOLOGY / PROCEDURE OF INSTALLATION OF
FALSE
CEILING:
Ø Firstly, all required measurements of ceiling (length and
width) and ceiling to wall (for height of false ceiling) shall be taken for
each room where false ceiling is to be installed.
Ø Material Requirement shall be calculated depending on
size i.e. area of rooms where it needs to be installed as per drawing
dimention.
Ø The ceiling levelling shall be marked with water tube.
The ceiling needs to be in one level for correct installation of false ceiling.
Ø After levelling procedure and marking is complete, marking
shall be done on ceiling at distance as per drawing.
Ø Marking shall be also done in side walls at the height
where the false ceiling will be suspended below the original ceiling.
Ø Hooks of metal ceiling angle strip shall be fixed to the
ceiling. These fittings become the chief support points of false ceiling.
Ø For framing, perimeter channels shall be fitted on the
walls at a height where false ceiling will be suspended.
Ø The perimeter channels and free end of hooks shall be connected
with other channels.
Ø This arrangement becomes the fixed section of false
ceiling that acts as the main foundation of false ceiling.
Ø To hang or support False ceiling from main ceiling,
Anchor fasteners if required shall be used. Anchor fasteners provide support to
secondary ceiling.
Ø Sufficient anchorage shall be provided it straight.
Ø Ceiling sections are then fitted to the main foundation
forming much précised framing that enables attaching ceiling board or any other
material used for false ceiling.
Ø The section joints created shall be connected by using
clips that offer strong and durable joints. These connecting clips also help
for easy installations of ceiling board.
Ø Once the framing is completed, wiring for lights, fan and other necessary electrical work shall be completed.
Ø Ceiling Board of approved thickness shall be attached to the framework with help of drywall screws.
Ø The joints and
edges shall be covered and finished
by using of jointing compound and paper tape or as recommended by client
(if required).
Ø Once the finishing process is over, MEP team shall be called to install light fittings and any other fittings
to do final wiring and other electrical work.
Ø The ceiling is now ready to be painted (in case of gypsum ceiling board).
Ø All the diagrams will be obtained at each stage.
Same procedure shall be followed for metal ceiling also.
Industries prefer sourcing HDPE sheets from Gujarat due to consistent quality and efficient logistics. Local suppliers ensure quick turnaround and bulk supply capabilities. Trusted HDPE Sheet for Cable drums suppliers in Gujarat provide strong, lightweight, and moisture-resistant sheets that enhance the lifespan of cable drums used in power and telecom sectors.
ReplyDelete