WORK METHODOLOGY
/ PROCEDURE OF KITCHEN PLATFORM OR COUNTER FIXING
Ø Before cutting and fixing of granite slab, visual colour
match shall be done to ensure that an acceptable colour match is achieved. Only
approved material shall be used.
Ø Detailed drawing shall be available at the time of fixing.
Ø The position & marking of vertical & horizontal
supports shall be marked on wall as per drawing
Ø All chiseling work for vertical & horizontal supports
shall be completed before plastering.
Ø The chiseling for sufficient bearing (at least 20 mm
deep) shall be done by cutter machine
only.
Ø The vertical support shall be in line & plumb
Ø Fixing of sub base of platform on the vertical support shall
be in line & level & in slope as specified.
Ø Sub base of platform shall be of 25mm thick Kadappa and
20mm thick cement mortar 1: 4 (1 Cement: 4 sand) or as per drawing.
Ø For vertical support 25mm thick Kadappa stone shall be
used or as per client recommendation or as per drawing.
Ø Ensure that the nahani trap shall be fixed at sink bottom
& sealing of the hole of outlet in wall with rich cement mortar.
Ø Ensure that proportion of mortar shall be 1 : 4 (01 Cement
: 04 Sand)
Ø Height of platform shall be as per drawing from FFL,
required slope shall be provided.
Ø Fascia shall be fixed as per details shown in drawing .
Ø A slot shall be left for gas pipe line in kitchen
platform.
Ø Hole shall be drilled in platform for inlet & outlet
pipes.
Ø All joints shall be filled with approved joint filler or
with white cement
Ø All edges of the top shall be rounded off & polished
Ø Top of platform shall be covered with POP. Required
finishes shall be done.
Ø Damaged material shall not be used.
Ø Sink will be properly fixed as per detail mentioned in
drawing.
Ø Cleaning shall be done properly.
Ø Curing should be done for min 3 to 5 days.