WORK METHODOLOGY / PROCEDURE OF EXTERNAL PAINTING
A.
Surface
Preparation
Ø For
external painting work at height, suitable arrangement shall be provided as per
approval of safety team.
Ø Provided
gondola, scaffolding shall be inspected with Safety officer prior to usage.
Ø Cleaning
of RCC surface shall be done where external painting to be done.
Ø Efflorescence,
chalk, dust, dirt, grease and oils shall be removed by using of sanding or
scraping.
Ø The
surface of the area to be painted would be prepared by removing loose
particles, blemishes and deleterious materials by way of scraping.
Ø Any
surface defects on RCC shall be repaired as per RCC repairing Procedure.
Ø All
tie patti or tie rod hole shall be filled with non-shrink grout materials.
Ø All
clearance will be obtained before starting of External painting activities.
Ø Slope
at required location to be maintained to avoid water stagnant. like; at window
sill, etc.
Ø Repairing
shall be done as per approved procedure and approved material.
Ø All
external groves shall be maintained properly as per drawing.
Ø All
MEP items shall be protected before starting of Painting activities.
B.
Application
of Two Coat Putty
Ø Proper
scraping shall be done on RCC surface by using of scraper patti.
Ø Approved
filling putty / coarse putty shall be applied uniformly on RCC / by using of
flat bladed plate or large putty knives with one in each hand.
Ø Thickness
of filling putty / coarse putty shall be of approx. 02 to 03 mm or as recommended by manufacture.
Ø Applied
putty shall be allowed to dry at least for 6 hrs. or as per technical data
sheet.
Ø After
drying of filling putty, second coat fine putty shall be applied.
Ø Thickness
of fine putty shall be of approx. 0.5 to 0.8 mm or as recommended by
manufacture.
Ø Once
the fine putty is fully applied and surface shall be allowed for drying for a
minimum period of 8 hrs.
C.
Application
of Texture
Ø Approved
Primer shall be applied on putty surface if required.
Ø Primer
shall be applied if time period is exceeded more than 10 days of application of
Wall Putty or as per manufacturer guideline.
Ø One
coat texture shall be applied at least after 4 to 6 hrs. of primer application if
Primer is applicable. Else texture will be applied after 8 to 10 hrs of wall
putty application.
Ø Minimum
time gap between Asian wall putty and texture shall be 8 to 10hrs or as per manufacturer
guideline.
Ø Thickness
of texture shall be of approx. 0.5 to 1.0 mm or as per project specification.
Ø Texture
coat shall be applied by using of roller brush or as per manufacturer guideline.
Ø After
application of texture, surface shall be allowed for air drying for a period of
at least 10 to 12 hrs. or as per manufacturer recommendation.
D.
Application
of Two Coat Paint
Ø The
surface to be painted shall be free from any loose paint, dust and oil &
grease.
Ø Any
visible surface cracks shall be repaired prior to start of painting.
Ø Two
coat of approved paint shall be applied
after 10 to 12hrs of Putty application.
Ø Primer
shall be applied if time period is exceeded more than 10 days of application of
texture or as per manufacturer guideline.
Ø First
coat paint shall be applied as per the approved RAL colour code.
Ø Applied
first coat paint shall be allowed to dry at least for 4 to 6 hrs as per manufacturer’s
recommendation.
Ø After
drying of first coat paint second coat paint shall be applied as per the
approved RAL colour code.
Ø Cleaning
of MEP items shall be done after completion of external painting.
External Paint system:
1 coat Coarse Putty /
filling putty + 1 Coat fine putty + Texture + 2 coat Paint