14. CHECKLIST
FOR BLOCK / BRICK MASONRY WORK |
|||
Name Of Project : |
|||
Date of Checking: |
|||
Location / Grid no: |
|||
Drawing / Document Reference No. |
|||
|
|||
Sl. |
Description / Activities / Items to
be Checked |
Status |
|
1 |
Check
the safety process is followed for the activities. |
OK |
Not OK |
PRIOR TO MASONRY WORK |
|||
2 |
Check for approval of work methodology for masonry work |
OK |
Not OK |
3 |
Check for Suitability & Safety of Scaffolding for masonry work |
OK |
Not OK |
4 |
Check for availability of Tool and tackles for masonry work. |
OK |
Not OK |
5 |
Check for approval of material to be used for masonry work |
OK |
Not OK |
6 |
Check for availability of materials for masonry work |
OK |
Not OK |
7 |
Check for cleanliness of concrete surface where block work to be
executed |
OK |
Not OK |
8 |
Check for hacking is done on RCC surface / application of bonding
agent at joint of RCC and masonry work |
OK |
Not OK |
9 |
Check for mix proportion of Cement mortar / Ready mix mortar / Block
jointing mortar |
OK |
Not OK |
10 |
Check for Moisturing of Masonry Blocks / Bricks before placing. |
OK |
Not OK |
11 |
Check for laying of DPC course before staring of Masonry work |
OK |
Not OK |
DURING MASONRY WORK |
|||
12 |
Check for laying of mortar bedding on DPC before first layer of block. |
OK |
Not OK |
13 |
Check for the Alignment & Location of Block Masonry as specified
in the Construction Drawings |
OK |
Not OK |
14 |
Check for the joint thickness of masonry work |
OK |
Not OK |
15 |
Check for Dimension, plumb and level of masonry work |
OK |
Not OK |
16 |
Check for Staggering of vertical joints of masonry work |
OK |
Not OK |
17 |
Size for opening of doors and windows |
OK |
Not OK |
18 |
Check for the dimensions of masonry work as per drawing |
OK |
Not OK |
19 |
Check for sizes of doors & windows openings |
OK |
Not OK |
20 |
Check for location of mullion and bend beam are provided as per
drawing |
OK |
Not OK |
21 |
Check for racking of joints to receive plastering or pointing (both
sides of wall) |
OK |
Not OK |
22 |
Check for provision of MEP services as per drawing. |
OK |
Not OK |
23 |
Check for metal packing at the top of masonry wall / below RCC beam
bottom |
OK |
Not OK |
24 |
Check for curing arrangements |
OK |
Not OK |
25 |
OK |
Not OK |
|
AFTER MASONRY WORK |
|||
26 |
Check for curing is being done properly. |
OK |
Not OK |
27 |
Check all mortar joints are raked and cleaned. |
OK |
Not OK |
28 |
Check that all flatwork has been cleaned and is scraped free of mortar
splatters. |
OK |
Not OK |
29 |
Check all waste block and mortar has been piled in designated trash
area. |
OK |
Not OK |
30 |
|
OK |
Not OK |
Remark: |
14. CHECKLIST FOR BLOCK / BRICK MASONRY WORK (AAC / CONCRETE BLOCK / BRICK WORK)
Subscribe to:
Post Comments (Atom)
-
23. CHECKLIST FOR FIXING OF FALSE CEILING Name Of Project : Date of Checking: Location / ...
-
METHODOLOGY / PROCEDURE OF CONVENTIONAL SHUTTERING & CONCRETING WORK TERMINOLOGY OF FORMWORK : Ø Formwork (Shuttering ) ...
-
26. CHECKLIST FOR VDF / TREMIX FLOORING Name Of Project : Date of Checking: Location / Fl...