3. CHECKLIST FOR SOIL EXCAVATION
& FILLING |
||||
Name Of Project : |
||||
Location / Grid no: |
||||
Date of Execution: |
||||
Drawing / Document
Reference No. |
||||
Soil Investigation
/ Test Report Ref. No: |
||||
|
||||
S.No. |
Description / Activities / Items to be Checked |
Status |
||
1 |
Check Excavation
Plan prepared and approved by Client / consultant |
OK |
Not OK |
|
2 |
Check Setting Out
and Levels Established and other survey work done as per Drawing |
OK |
Not OK |
|
3 |
Checked for underground
utilities. |
OK |
Not OK |
|
4 |
Check Safe better
slop/Ground support plan established with conform no effect on adjacent
works. |
OK |
Not OK |
|
5 |
Is layout,
alignment and size of excavation marked on ground as per excavation plan? |
OK |
Not OK |
|
6 |
Check for dewatering
arrangements |
OK |
Not OK |
|
7 |
Check area
identified for disposal of excavated soil |
OK |
Not OK |
|
Filling |
||||
1 |
Check that
protective coating to foundation is carried out and curing time is completed. |
OK |
Not OK |
|
2 |
Check
water-proofing to structures, if applicable is carried out as per
specification. |
OK |
Not OK |
|
3 |
Check base is clean
and free of stones and debris. |
OK |
Not OK |
|
4 |
Check necessary
demarcation for base line and Temporary Bench Mark (TBM) is established for
reference level. |
OK |
Not OK |
|
5 |
Check the approval
of soil to be used for filling. |
OK |
Not OK |
|
6 |
Check availability
of suitable compacting equipment is available. |
OK |
Not OK |
|
7 |
Check necessary
level demarcation is made for layer wise filling. |
OK |
Not OK |
|
8 |
Check and ensure
placement of fill in layer of 200 mm maximum and each layer is well
compacted. |
OK |
Not OK |
|
9 |
Check field
compaction test where applicable was conducted and recorded. |
OK |
Not OK |
|
Remark: |
||||
3. CHECKLIST FOR SOIL EXCAVATION & FILLING
Subscribe to:
Post Comments (Atom)
-
23. CHECKLIST FOR FIXING OF FALSE CEILING Name Of Project : Date of Checking: Location / ...
-
METHODOLOGY / PROCEDURE OF CONVENTIONAL SHUTTERING & CONCRETING WORK TERMINOLOGY OF FORMWORK : Ø Formwork (Shuttering ) ...
-
26. CHECKLIST FOR VDF / TREMIX FLOORING Name Of Project : Date of Checking: Location / Fl...
No comments:
Post a Comment