21. CHECKLIST FOR FIXING OF ALUMINIUM SLIDING
WINDOWS |
|||
Name Of Project : |
|||
Date of Checking: |
|||
Location / Flat / Floor no: |
|||
Drawing / Document Reference No. |
|||
|
|||
Sl. |
Description / Activities / Items to
be Checked |
Status |
|
1 |
Check
for the safety process is followed for fixing of Aluminium Sliding Window. |
OK |
Not OK |
|
|
|
|
PRIOR TO FIXING OF ALUMINIUM SECTION |
|||
1 |
Check for approval of work methodology for fixing of aluminium sliding
Window. |
OK |
Not OK |
2 |
Check for availability of Tool and tackles for fixing of aluminium
sliding Window. |
OK |
Not OK |
3 |
Check for the grade of aluminium section is used as per specification. |
OK |
Not OK |
4 |
Check the shape & size of the aluminium sections are cut as per
drawing. |
OK |
Not OK |
5 |
Check for the top level of the aluminium sliding Window is marked on
the wall. |
OK |
Not OK |
6 |
Check for the inspection of incoming materials w.r.t. Specification. |
OK |
Not OK |
7 |
Check for the coating of aluminium section is done as per the approved
shade. |
OK |
Not OK |
8 |
Check for the protection of coated aluminium section is done. |
OK |
Not OK |
DURING FIXING OF ALUMINIUM SECTION. |
|||
1 |
Check for the Section type is used. (2 track / 3 track) |
OK |
Not OK |
2 |
Check the plumb of the window frame w.r.t. opening. |
OK |
Not OK |
3 |
Check for the L clip is used at corner of the sections for proper
assembling. |
OK |
Not OK |
4 |
Check for PVC packing is used for packing / aligning of window frames. |
OK |
Not OK |
5 |
Check for proper fastening of window frames/sub frame to walls by
screws. |
OK |
Not OK |
6 |
Check for no of screws are fixed as per drawing. |
OK |
Not OK |
7 |
Check for dimension of the frames before final screwing of aluminium
Frames. |
OK |
Not OK |
8 |
Check for fixing of glass shutter as per required size. |
OK |
Not OK |
9 |
Check for the thickness, brand & types of glass is used for window
shutters. |
OK |
Not OK |
10 |
Check for the fixing of the hardware fittings as per drawing. |
OK |
Not OK |
AFTER FIXING OF SLIDING WINDOW |
|||
1 |
Check for the proper functioning of hardware fittings Like; Hinges,
Roller, Handles, Locks, EPDM gaskets, etc. |
OK |
Not OK |
2 |
Check for overall satisfactory functioning of Windows. |
OK |
Not OK |
3 |
Check for removal of protective coating & cleaning of the
aluminium window before handing over. |
OK |
Not OK |
4 |
Check for the fixing of backer rod on periphery of the aluminium
section before application of Sealant. |
OK |
Not OK |
5 |
Check for the water leakage test of the window. (if required) |
OK |
Not OK |
Remarks: |
21. CHECKLIST FOR FIXING OF ALUMINIUM SLIDING WINDOWS
Subscribe to:
Post Comments (Atom)
-
23. CHECKLIST FOR FIXING OF FALSE CEILING Name Of Project : Date of Checking: Location / ...
-
METHODOLOGY / PROCEDURE OF CONVENTIONAL SHUTTERING & CONCRETING WORK TERMINOLOGY OF FORMWORK : Ø Formwork (Shuttering ) ...
-
26. CHECKLIST FOR VDF / TREMIX FLOORING Name Of Project : Date of Checking: Location / Fl...
No comments: