15. CHECKLIST FOR PLASTER WORK FOR INTERNAL & EXTERNAL (CEMENT MORTAR)

 

15.    CHECKLIST FOR PLASTER WORK  (CEMENT MORTAR)

Name Of Project :

Date of Checking:

Location / Grid no:

Drawing / Document Reference No.

 

Sl.
No.

Description / Activities / Items to be Checked

Status

1

Check for the safety process is followed for plaster activities.

OK

Not OK

PRIOR TO PLASTER WORK

2

Check for approval of work methodology for plaster work

OK

Not OK

3

Check for Suitability & Safety of Scaffolding for plaster work

OK

Not OK

4

Check for availability of Tool and tackles for plaster work

OK

Not OK

5

Check for approval of material to be used for plaster work.

OK

Not OK

6

Check for availability of materials for plaster work.
Like; cement & sand / Ready mix plaster, water, GI / Fibre mesh, etc..

OK

Not OK

7

Check for cleanliness of concrete / masonry surface where plaster work to be executed

OK

Not OK

8

Check for hacking is done on RCC surface / application of bonding agent on RCC surface.
(Bonding agent must be applied at least 24 hrs before)

OK

Not OK

9

Check for Moisturing of Masonry surface before plastering.

OK

Not OK

10

Check for fixing of GI / Fibre mesh at the joint of RCC & masonry work.

OK

Not OK

11

Check for fixing of Door & Window frames and it's protection

OK

Not OK

12

Check for the level pads

OK

Not OK

13

Check for completion of MEP activities before start of Plastering.

OK

Not OK

14

Check for proper protection of MEP items before start of Plastering activities.

OK

Not OK

15

 

OK

Not OK

DURING PLASTER WORK

16

Check for mix proportion of Cement mortar / Ready mix mortar

OK

Not OK

17

Check for addition of waterproofing compound, if required.

OK

Not OK

18

Check for true level surface, right angle, plumb, edge, sharp corners.

OK

Not OK

19

Check for architectural features like grooves, bands etc.

OK

Not OK

20

Check for Waviness of plastered surface.

OK

Not OK

21

Check for Straightness of Edges of plaster surface.

OK

Not OK

22

Check for Right Angles & Plumb of plaster surface.

OK

Not OK

23

 

OK

Not OK

AFTER PLASTERING

24

Check for Removal of Dead Mortar and Debris

OK

Not OK

25

Check Date of Plastering is marked on the surface.

OK

Not OK

26

Check for Curing arrangements

OK

Not OK

27

Check for cleanliness of MEP items, door & window frames, etc.

OK

Not OK