2. CHECKLIST FOR SITE SETTING OUT |
|||
Name Of Project : |
|||
Location / Grid no: |
|||
Date of Execution: |
|||
Drawing / Document
Reference No. |
|||
Soil Investigation
/ Test Report Ref. No: |
|||
|
|||
S.No. |
Description / Activities / Items to be Checked |
Status |
|
1 |
Check for the proper
tool and tackles are available in site. |
OK |
Not OK |
2 |
Check for the
calibration of the survey equipments. |
OK |
Not OK |
3 |
Has the bench mark
been transferred from the permanent structure as mentioned in the drawing? |
OK |
Not OK |
4 |
Check for the
establishment & cross check of the TBM with permanent bench mark |
OK |
Not OK |
5 |
Check for all the
sides of the building are as per the setting out drawing |
OK |
Not OK |
6 |
Check for the
marking of the foundation transferred properly from the reference grids line |
OK |
Not OK |
7 |
Check for the
foundation / footings lines are marked properly as per drawing. |
OK |
Not OK |
8 |
|
OK |
Not OK |
9 |
|
OK |
Not OK |
Remark: |
2. CHECKLIST FOR SITE SETTING OUT
Subscribe to:
Post Comments (Atom)
-
23. CHECKLIST FOR FIXING OF FALSE CEILING Name Of Project : Date of Checking: Location / ...
-
METHODOLOGY / PROCEDURE OF CONVENTIONAL SHUTTERING & CONCRETING WORK TERMINOLOGY OF FORMWORK : Ø Formwork (Shuttering ) ...
-
26. CHECKLIST FOR VDF / TREMIX FLOORING Name Of Project : Date of Checking: Location / Fl...
No comments:
Post a Comment