10. CHECKLIST
FOR CHEMICAL WATERPROOFING WITH
BRICK BAT |
|||
|
Name Of Project : |
|||
|
Date of Checking: |
|||
|
Location / Structure: |
|||
|
Drawing / Document Reference No. |
|||
|
|
|||
|
Sl. |
Description / Activities / Items to
be Checked |
Status |
|
|
1 |
Check
for the safety process is followed for waterproofing activities. |
OK |
Not OK |
|
2 |
Check for approval of work methodology of waterproofing |
OK |
Not OK |
|
3 |
Check for approval of Waterproofing system and Chemicals to be used. |
OK |
Not OK |
|
PRIOR TO CHEMICAL COATING |
|||
|
1 |
Check for Cleaning of bare slab like removal and cleaning of oil,
grease, dead concrete / mortar, dust, any exposed steel, wood pieces, etc. |
OK |
Not OK |
|
2 |
Check for Ponding test to be done for 24 hours to find any leakages |
OK |
Not OK |
|
3 |
Check for nozzle grouting is done by using of integral waterproof
compound with cement slurry if any leakage is observed during Pond test. |
OK |
Not OK |
|
4 |
Check for the making of corner batta / hunch filling by cement mortar
with mixing of integral waterproofing chemicals. |
OK |
Not OK |
|
5 |
Check for availability of material and tools as per procedure /method
statement. |
OK |
Not OK |
|
DURING APPLICATION OF WP CHEMICALS |
|||
|
1 |
Check and ensured that slab cleaned from dust and other particles |
OK |
Not OK |
|
2 |
Check Mixing of polymer base Chemical and cement with proper
proportions by mechanical stirrer as per manufacturer guidelines before ready
to use on substrate. |
OK |
Not OK |
|
3 |
Check application of 1 st coat of polymer base chemical on substrate
as per manufacturer guidelines. |
OK |
Not OK |
|
4 |
Check application of 2 nd coat or subsequent coat after 4hrs
perpendicular in the direction of 1st coat. |
OK |
Not OK |
|
5 |
Check chemical application minimum up to the required height as per
project specification. |
OK |
Not OK |
|
6 |
Check for the consumption of chemicals as per methodology. |
OK |
Not OK |
|
7 |
Check Sprinkling of sand over the 2nd coat of chemical for mechanical
bonding with protection coat of plaster. |
OK |
Not OK |
|
AFTER APPLICATION OF WP CHEMICAL |
|||
|
1 |
Check Pond Test for 48hrs after drying chemical coat. |
OK |
Not OK |
|
2 |
Ensure no leakage & damage on waterproof surface |
OK |
Not OK |
|
DURING BRICK BAT |
|||
|
1 |
Laying 15-20mm thick cement sand mortar of 1: and admixed with
integral waterproofing compound @200ml/bag of cement or as per manufacturer’s
guidelines as a base mortar for Brickbats |
OK |
Not OK |
|
2 |
Ensure laying min.75mm thick brick bats of varying sizes over the
mortar in a gradient of 1:150 with varying thickness as per site condition. |
OK |
Not OK |
|
3 |
Is the Brick bats pre-wetted before laying |
OK |
Not OK |
|
4 |
Is the minimum half portion of brickbats should be immersed in mortar
and staggered joint between two brickbats |
OK |
Not OK |
|
AFTER BRRICK BAT |
|||
|
1 |
Check the curing for 7days |
|
|
|
2 |
|
|
|
|
REMARKS: |
|||
10. CHECKLIST FOR CHEMICAL WATERPROOFING WITH BRICK BAT
Subscribe to:
Post Comments (Atom)
-
23. CHECKLIST FOR FIXING OF FALSE CEILING Name Of Project : Date of Checking: Location / ...
-
METHODOLOGY / PROCEDURE OF CONVENTIONAL SHUTTERING & CONCRETING WORK TERMINOLOGY OF FORMWORK : Ø Formwork (Shuttering ) ...
-
14. CHECKLIST FOR BLOCK / BRICK MASONRY WORK (AAC / CONCRETE BLOCK / BRICK WORK) Name Of Project : ...
Nice Blog! Are you looking for terrace waterproofing in Panchkula? We provide top-quality waterproofing services at a reasonable price. We provide customer satisfaction with our waterproofing services. We provide 100% permanent solutions for terraces and 24*7 available for our customers. Our well-qualified team uses different methods and technology for waterproofing work.
ReplyDeleteExport businesses in Gujarat hold a strong reputation worldwide for offering reliable products. Many cable industries rely on HDPE Sheet for Cable Reels Exporter in Gujarat because they provide superior quality, durable, and weather-resistant sheets. Gujarat has emerged as a leading hub for HDPE products, delivering both domestic and international demands. Exporters from this region ensure competitive prices and timely deliveries, helping businesses maintain efficiency in production and supply chain management.
ReplyDelete